ADU Ledger

Does an Everett detached ADU really need its own water meter?

✓ Verified against code · August 19, 2026

Yes — detached ADUs require a separate metered water service (and a dedicated side sewer, with limited shared exceptions). Budget for it; it routinely surprises people comparing city costs.

Citation: EMC 14.16.430

How current is this?

Everett’s ADU rules run under EMC 19.08.100 Table 8-6, under the Everett 2044 zoning (NR / NR-C) (Ordinances 4101-25 / 4102-25). The Everett 2044 periodic update, effective July 8, 2025, rewrote Title 19, deleted the owner-occupancy requirement, and abolished the old R-S/R-1/R-2 zones — any source citing those zones is describing a code that no longer exists. A housekeeping ordinance (CB 2512-91, January 2026) is already amending the new code, with more expected. We verified this answer against primary sources on August 19, 2026, and every change we catch is logged in the changelog.

More Everett ADU questions

All Everett ADU rules → · Compare Washington cities →

Not legal advice — lot-specific overlays can change the answer for your parcel. The citation above points at the governing code section; check it, or ask the city to confirm.